Upgrading Of Kitende Dispensary(fencing And Gate)

Completed GoMC-PMTS-2024-7483
Project Description

Fencing and Gate installation

Budget & Expenditure
Approved
KES 1.50M
Contract
KES 1.44M
Spent
KES 1.44M
Utilisation
96%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-7483
  • WardNguu/Masumba
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Health Services
  • DirectorateCurative and Rehabilitative Services
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start01 Dec 2023
  • End02 Mar 2024
Timeline
Cabinet Paper Approved
Phase One · 10 Nov 2023
Approved Requisition
Phase Two · 18 Nov 2023
Floated
Phase Two · 19 Nov 2023
Awarded
Phase Two · 30 Nov 2023
Site Handover
Phase Three · 04 Dec 2023
Not Started
Phase Two · 04 Dec 2023
Ongoing
Phase Three · 12 Dec 2023
Completed
Phase Three · 01 Feb 2024