Isuuni Drift

Completed GoMC-PMTS-2024-3104
Project Description

- Non-vented reinforced concrete drift  construction 

- Cut off drains for road run off harvesting

- Installation of gabions

Budget & Expenditure
Approved
KES 11.00M
Contract
KES 9.72M
Spent
KES 9.72M
Utilisation
88.4%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-3104
  • WardKithungo/Kitundu
  • Sub-CountyMbooni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start26 Feb 2024
  • End24 May 2024
Timeline
Cabinet Paper Approved
Phase One · 20 Sep 2023
Approved Requisition
Phase Two · 07 Dec 2023
Floated
Phase Two · 15 Dec 2023
Awarded
Phase Two · 19 Feb 2024
Site Handover
Phase Three · 20 Feb 2024
Not Started
Phase Two · 20 Feb 2024
Ongoing
Phase Three · 26 Feb 2024
Completed
Phase Three · 20 Mar 2024