Construction Of Kwa Kalelo - Winzeni Drift

Completed GoMC-PMTS-2024-8214
Project Description

Construction of kwa Kalelo - Winzeni drift

Budget & Expenditure
Approved
KES 4.00M
Contract
KES 3.81M
Spent
KES 3.81M
Utilisation
95.2%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8214
  • WardKitise/Kithuki
  • Sub-CountyMakueni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start21 Jun 2024
  • End23 Sep 2024
Timeline
Cabinet Paper Approved
Phase One · 03 Apr 2024
Approved Requisition
Phase Two · 15 Apr 2024
Floated
Phase Two · 25 Apr 2024
Awarded
Phase Two · 18 Jun 2024
Site Handover
Phase Three · 24 Jun 2024
Not Started
Phase Two · 24 Jun 2024
Ongoing
Phase Three · 27 Jun 2024
Completed
Phase Three · 30 Aug 2024