Upgrading Ngwata Maternity Centre

Completed GoMC-PMTS-2024-4501
Project Description

Construction of new OPD block

Budget & Expenditure
Approved
KES 5.35M
Contract
KES 4.74M
Spent
KES 4.74M
Utilisation
88.7%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-4501
  • WardMasongaleni
  • Sub-CountyKibwezi East
  • DepartmentDepartment of Health Services
  • DirectorateCurative and Rehabilitative Services
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start01 Mar 2024
  • End30 May 2024
Timeline
Cabinet Paper Approved
Phase One · 29 Nov 2023
Approved Requisition
Phase Two · 05 Dec 2023
Floated
Phase Two · 18 Jan 2024
Awarded
Phase Two · 22 Feb 2024
Site Handover
Phase Three · 03 Mar 2024
Not Started
Phase Two · 03 Mar 2024
Ongoing
Phase Three · 05 Mar 2024
Completed
Phase Three · 30 Apr 2024