Upgrading Ngai Health Center

Completed Flagship GoMC-PMTS-2024-5306
Project Description

PROPOSED CONSTRUCTION OF MATERNITY BLOCK 

Budget & Expenditure
Approved
KES 4.90M
Contract
KES 4.75M
Spent
KES 4.74M
Utilisation
96.8%
Budget Utilisation
Gallery (2 photos)
Ngai Upgrading
Ngai Upgrading
Ngai Upgrading
Ngai Upgrading
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-5306
  • WardKithungo/Kitundu
  • Sub-CountyMbooni
  • DepartmentDepartment of Health Services
  • DirectorateCurative and Rehabilitative Services
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryFlagship
  • Start21 Dec 2023
  • End22 Mar 2024
Timeline
Cabinet Paper Approved
Phase One · 02 Nov 2023
Approved Requisition
Phase Two · 21 Nov 2023
Floated
Phase Two · 01 Dec 2023
Awarded
Phase Two · 20 Dec 2023
Site Handover
Phase Three · 03 Jan 2024
Not Started
Phase Two · 03 Jan 2024
Ongoing
Phase Three · 10 Jan 2024
Completed
Phase Three · 09 Feb 2024