Upgrading Kithyululu Model Health Centre

Completed Flagship GoMC-PMTS-2024-6497
Project Description
Renovation of maternity block, construction of staff house, construction of soak pit.
Budget & Expenditure
Approved
KES 1.78M
Contract
KES 4.75M
Spent
KES 2.19M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-6497
  • WardMasongaleni
  • Sub-CountyKibwezi East
  • DepartmentDepartment of Health Services
  • DirectorateCurative and Rehabilitative Services
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryFlagship
  • Start21 Dec 2023
  • End21 Mar 2024
Timeline
Cabinet Paper Approved
Phase One · 02 Nov 2023
Approved Requisition
Phase Two · 16 Nov 2023
Floated
Phase Two · 01 Dec 2023
Awarded
Phase Two · 20 Dec 2023
Site Handover
Phase Three · 03 Jan 2024
Not Started
Phase Two · 03 Jan 2024
Ongoing
Phase Three · 10 Jan 2024
Completed
Phase Three · 25 Mar 2025