Upgrading Kathonzweni Health Center.

Completed Flagship GoMC-PMTS-2024-6631
Project Description

Upgrading of the facility

Budget & Expenditure
Approved
KES 685.4K
Contract
KES 685.4K
Spent
KES 684.6K
Utilisation
99.9%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-6631
  • WardKathonzweni
  • Sub-CountyMakueni
  • DepartmentDepartment of Health Services
  • DirectoratePreventive and Promotive Services
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryFlagship
  • Start27 Jun 2024
  • End25 Aug 2024
Timeline
Cabinet Paper Approved
Phase One · 19 Mar 2024
Approved Requisition
Phase Two · 21 Mar 2024
Refloated
Phase One · 06 May 2024
Awarded
Phase Two · 27 Jun 2024
Site Handover
Phase Three · 27 Jun 2024
Not Started
Phase Two · 27 Jun 2024
Ongoing
Phase Three · 28 Jun 2024
Completed
Phase Three · 16 Dec 2024