Installation Of 8.5m Double Arm Integrated Solar Lights System Mavivye Market

Completed GoMC-PMTS-2024-1799
Project Description

Installation of double arm metallic pole 8.5m high , fixing of 150W integrated solar streetlight system at Mavivye market

Budget & Expenditure
Approved
KES 245.0K
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-1799
  • WardKiima Kiu/Kalanzoni
  • Sub-CountyKilome
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateEnergy
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start01 Dec 2023
  • End20 Feb 2024
Timeline
Cabinet Paper Approved
Phase One · 15 Aug 2023
Approved Requisition
Phase Two · 18 Oct 2023
Floated
Phase Two · 20 Oct 2023
Awarded
Phase Two · 15 Dec 2023
Site Handover
Phase Three · 29 Nov 2023
Not Started
Phase Two · 01 Dec 2023
Ongoing
Phase Three · 01 Dec 2023
Completed
Phase Three · 23 Feb 2024