Agricultural And Livestock Productivity

Completed GoMC-PMTS-2024-4869
Project Description

Agricultural and livestock productivity- Provision of subsidized AI services , Extension programme and construction of 5 cattle crushes

Budget & Expenditure
Approved
KES 2.00M
Contract
KES 1.34M
Spent
KES 824.0K
Utilisation
41.2%
Budget Utilisation
Citizen Feedback
Vetelo 16 Jun 2024
Agricultural And Livestock Productivity

Kindly I Would Like To Know In Which Areas Is The Construction Going On

Official Response:

Tutini, Kwa Kavoo, Kwa Kokote, Nzele and Matiliku Cattle Crushes. Thank you for your feedback

Project Details
  • RefGoMC-PMTS-2024-4869
  • WardEmali/Mulala
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Agriculture, Livestock, Fisheries &
  • DirectorateLivestock and Fisheries Development
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start15 Apr 2003
  • End15 Jul 2023
Timeline
Cabinet Paper Approved
Phase One · 16 Dec 2022
Approved Requisition
Phase Two · 15 Mar 2023
Floated
Phase Two · 08 Mar 2023
Awarded
Phase Two · 14 Apr 2023
Site Handover
Phase Three · 15 Apr 2023
Not Started
Phase Two · 15 Apr 2023
Ongoing
Phase Three · 15 Apr 2023
Completed
Phase Three · 31 Jan 2024