Installation Of Floodlights

Completed GoMC-PMTS-2024-4175
Project Description

Installation of double arm metallic pole 8.5m high , fixing of 150W integrated solar streetlights fittings

Budget & Expenditure
Approved
KES 1.96M
Contract
KES 3.34M
Spent
KES 3.33M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-4175
  • WardKitise/Kithuki
  • Sub-CountyMakueni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateEnergy
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start21 Dec 2023
  • End29 Apr 2024
Timeline
Cabinet Paper Approved
Phase One · 27 Aug 2023
Approved Requisition
Phase Two · 29 Aug 2023
Floated
Phase Two · 21 Sep 2023
Awarded
Phase Two · 18 Oct 2023
Site Handover
Phase Three · 24 Nov 2023
Not Started
Phase Two · 24 Nov 2023
Ongoing
Phase Three · 08 Dec 2023
Completed
Phase Three · 16 May 2024