Installation Of Flood Light Masts At Makindu Upper Market

Completed GoMC-PMTS-2024-3902
Project Description

Installation of starter bars, Installation of polygon 20m high pole, fixing of 9no. 400W fittings , Installation of manual/automatic pulleys and winches, kplc metering of the mast.

Budget & Expenditure
Approved
KES 2.94M
Contract
KES 2.94M
Spent
KES 2.47M
Utilisation
83.9%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-3902
  • WardMakindu
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateEnergy
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start30 Nov 2023
  • End30 Nov 2023
Timeline
Cabinet Paper Approved
Phase One · 18 Sep 2023
Approved Requisition
Phase Two · 19 Sep 2023
Floated
Phase Two · 05 Jan 2024
Awarded
Phase Two · 30 Nov 2023
Site Handover
Phase Three · 30 Nov 2023
Not Started
Phase Two · 30 Nov 2023
Ongoing
Phase Three · 30 Nov 2023
Completed
Phase Three · 09 Apr 2024