Kithuki Sub-ward Administrator's Office

Completed GoMC-PMTS-2024-9529
Project Description

Renovation of Administrator's Office

Budget & Expenditure
Approved
KES 651.6K
Contract
KES 631.9K
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Gallery (1 photos)
Kitise Sub-ward Administration Office
Kitise Sub-ward Administration Office
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-9529
  • WardKitise/Kithuki
  • Sub-CountyMakueni
  • DepartmentDepartment of Devolution, Public Service, Public
  • DirectorateCounty Administration
  • FY2023/2024
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
  • Start11 Mar 2024
  • End11 Jun 2024
Timeline
Cabinet Paper Approved
Phase One · 15 Jan 2024
Approved Requisition
Phase Two · 16 Jan 2024
Floated
Phase Two · 02 Feb 2024
Awarded
Phase Two · 08 Mar 2024
Site Handover
Phase Three · 28 Mar 2024
Not Started
Phase Two · 28 Mar 2024
Ongoing
Phase Three · 02 Apr 2024
Completed
Phase Three · 21 May 2024