Kibwezi Town Lighting Programme ( Matundani Floodlight, Kibwezi Streetlighting)

Completed GoMC-PMTS-2024-3722
Project Description

Installation of starter bars, Installation of polygon 20m high pole, fixing of 6no. 400W fittings , Installation of manual/automatic pulleys and winches, kplc metering of the mast.

Budget & Expenditure
Approved
KES 3.82M
Contract
KES 1.99M
Spent
KES 2.08M
Utilisation
54.4%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-3722
  • WardKikumbulyu South
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateEnergy
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start01 Nov 2023
  • End31 Jan 2024
Timeline
Cabinet Paper Approved
Phase One · 27 Aug 2023
Approved Requisition
Phase Two · 30 Aug 2023
Floated
Phase Two · 08 Sep 2023
Awarded
Phase Two · 10 Nov 2023
Site Handover
Phase Three · 23 Oct 2023
Not Started
Phase Two · 23 Oct 2023
Ongoing
Phase Three · 01 Nov 2023
Completed
Phase Three · 26 Jan 2024