Road Improvement Program (fuel For Road Maintanance)

Completed GoMC-PMTS-2024-6690
Project Description

Light grading along

1. Mbumbuni-Ndumbi Road 10km

2. Mbumbuni-Iviani-Mukimwani Road (6km)

3. Mbumbuni-Kalimani-Kwa Kalenga Road (4km)

4. Lung’uni-Kavuvoni Primary School Road (3km)

5.Mbumbuni-Kalimani Road (2.5km)

6. Ngoni-Kisekini Road (5.5km)

7. Mbumbuni-Kalimani-Mukimwani Road (11.5Km)

Budget & Expenditure
Approved
KES 1.00M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-6690
  • WardKisau/Kiteta
  • Sub-CountyMbooni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 10 Oct 2023
Approved Requisition
Phase Two · 07 Dec 2023
Ongoing
Phase Three · 20 Feb 2024
Completed
Phase Three · 30 Aug 2024