Ulilinzi Mkt Livestock Yard

Completed GoMC-PMTS-2024-7413
Project Description

contruction of two compactment on two acre land , two door latrine with urenal 

Budget & Expenditure
Approved
KES 2.00M
Contract
KES 1.99M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-7413
  • WardAll Wards
  • Sub-CountyKibwezi East
  • DepartmentDepartment of Agriculture, Livestock, Fisheries &
  • DirectorateLivestock and Fisheries Development
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start18 May 2023
  • End25 Aug 2023
Timeline
Cabinet Paper Approved
Phase One · 16 Dec 2022
Approved Requisition
Phase Two · 03 Mar 2023
Floated
Phase Two · 13 Apr 2023
Awarded
Phase Two · 04 May 2023
Site Handover
Phase Three · 25 Aug 2023
Not Started
Phase Two · 18 May 2023
Ongoing
Phase Three · 18 May 2023
Completed
Phase Three · 25 Aug 2023