Kibwezi Town Roads Improvement

Completed GoMC-PMTS-2024-1641
Project Description

Road opening,

2.65km spot gravelling,

2.8km of road grading

Budget & Expenditure
Approved
KES 4.41M
Contract
KES 4.28M
Spent
KES 4.27M
Utilisation
96.8%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-1641
  • WardKikumbulyu South
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start21 Feb 2024
  • End24 May 2024
Timeline
Cabinet Paper Approved
Phase One · 20 Sep 2023
Approved Requisition
Phase Two · 07 Dec 2023
Floated
Phase Two · 18 Jan 2024
Awarded
Phase Two · 28 Feb 2024
Site Handover
Phase Three · 21 Feb 2024
Not Started
Phase Two · 21 Feb 2024
Ongoing
Phase Three · 21 Feb 2024
Completed
Phase Three · 02 Apr 2024