Mechanical road opening-4.7km,
heavy grading-4.7km, installation of culverts-64M , Gabions -20N, and and cut
off mitre-800M drains for road run-off harvesting along Makasa primary - Thuti -Utini road
Budget & Expenditure
Approved
KES 4.90M
Contract
KES 4.03M
Spent
KES 4.03M
Utilisation
82.2%
Budget Utilisation
Citizen Feedback
Project Details
RefGoMC-PMTS-2024-4014
WardNguu/Masumba
Sub-CountyKibwezi West
DepartmentDepartment of Infrastructure, Transport, Public Wo
DirectorateInfrastructure, Transport and Public works