Ukaatuni Ctti

Completed GoMC-PMTS-2024-4237
Project Description

Equipping 

Budget & Expenditure
Approved
KES 1.75M
Contract
KES 1.62M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-4237
  • WardUkia
  • Sub-CountyKaiti
  • DepartmentDepartment of ICT, Education and Internship
  • DirectorateTechnical Training
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start22 Apr 2024
  • End22 May 2024
Timeline
Cabinet Paper Approved
Phase One · 12 Feb 2024
Approved Requisition
Phase Two · 19 Feb 2024
Floated
Phase Two · 14 Mar 2024
Awarded
Phase Two · 22 Apr 2024
Site Handover
Phase Three · 22 Apr 2024
Not Started
Phase Two · 22 Apr 2024
Ongoing
Phase Three · 22 Apr 2024
Completed
Phase Three · 26 Mar 2025