Migingo Parking

Completed GoMC-PMTS-2024-8939
Project Description

Road gravelling and compaction 

Budget & Expenditure
Approved
KES 980.0K
Contract
KES 941.8K
Spent
KES 1.94M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8939
  • WardIvingoni/Nzambani
  • Sub-CountyKibwezi East
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start02 Jan 2024
  • End02 May 2024
Timeline
Cabinet Paper Approved
Phase One · 04 Oct 2023
Approved Requisition
Phase Two · 09 Nov 2023
Floated
Phase Two · 23 Nov 2023
Awarded
Phase Two · 11 Dec 2023
Site Handover
Phase Three · 27 Dec 2023
Not Started
Phase Two · 11 Dec 2023
Ongoing
Phase Three · 11 Dec 2023
Completed
Phase Three · 05 Jan 2024