Kilome Sub-county Administration Office

Completed GoMC-PMTS-2024-2724
Project Description

Construction of office block

Budget & Expenditure
Approved
KES 9.00M
Contract
KES 8.38M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Gallery (1 photos)
Kilome Sub-county Administrator's Office
Kilome Sub-county Administrator's Office
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-2724
  • WardMukaa
  • Sub-CountyKilome
  • DepartmentDepartment of Devolution, Public Service, Public
  • DirectorateCounty Administration
  • FY2023/2024
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
  • Start25 Jan 2024
  • End26 Aug 2024
Timeline
Cabinet Paper Approved
Phase One · 30 Oct 2023
Approved Requisition
Phase Two · 06 Nov 2023
Floated
Phase Two · 28 Nov 2023
Awarded
Phase Two · 09 Jan 2024
Site Handover
Phase Three · 02 Feb 2024
Not Started
Phase Two · 02 Feb 2024
Ongoing
Phase Three · 02 Feb 2024
Completed
Phase Three · 09 May 2024