Road Improvement Programme

Completed GoMC-PMTS-2024-2167
Project Description

Road grading

spot murraming  and installation of drainage structures

Budget & Expenditure
Approved
KES 3.00M
Contract
KES 3.16M
Spent
KES 300.0K
Utilisation
10%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-2167
  • WardThange
  • Sub-CountyKibwezi East
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start10 Jan 2024
  • End30 May 2024
Timeline
Cabinet Paper Approved
Phase One · 04 Oct 2023
Approved Requisition
Phase Two · 08 Feb 2024
Floated
Phase Two · 24 Nov 2023
Awarded
Phase Two · 03 Jan 2024
Site Handover
Phase Three · 11 Jan 2024
Not Started
Phase Two · 11 Jan 2024
Ongoing
Phase Three · 11 Jan 2024
Completed
Phase Three · 23 Oct 2024