Road Improvement

Completed GoMC-PMTS-2024-2786
Project Description

Road improvement -light grading

Budget & Expenditure
Approved
KES 1.96M
Contract
KES 1.96M
Spent
KES 1.50M
Utilisation
76.4%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-2786
  • WardUkia
  • Sub-CountyKaiti
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start26 Feb 2024
  • End20 Apr 2024
Timeline
Cabinet Paper Approved
Phase One · 20 Sep 2023
Approved Requisition
Phase Two · 26 Sep 2023
Floated
Phase Two · 02 Nov 2023
Awarded
Phase Two · 21 Feb 2024
Site Handover
Phase Three · 21 Feb 2024
Not Started
Phase Two · 21 Feb 2024
Ongoing
Phase Three · 26 Feb 2024
Completed
Phase Three · 08 Feb 2024