Makueni Dairy Farmers Cooperative Society

Completed Flagship GoMC-PMTS-2026-9158
Project Description

Installation of 3 phase charge controllers, 60 solar panels, PV cables, inverters, lithium batteries, battery racking etc .and installation costs

Budget & Expenditure
Approved
KES 4.34M
Contract
KES 0.00
Spent
KES 4.03M
Utilisation
92.7%
Budget Utilisation
Gallery (3 photos)
The Plant
The Plant
Makueni Dairy
Makueni Dairy
Pictorial Evidence Makueni Dairy
Pictorial Evidence Makueni Dairy
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2026-9158
  • WardWote/Nziu
  • Sub-CountyMakueni
  • DepartmentDepartment of Agriculture, Livestock, Fisheries &
  • DirectorateCooperative Development
  • FY2025/2026
  • SourceDonor funds
  • Funded FromHeadquaters
  • CategoryFlagship
  • Start04 Dec 2025
  • End19 Feb 2026
Timeline
Cabinet Paper Approved
Phase One · 01 Jul 2025
Approved Requisition
Phase Two · 15 Aug 2025
Floated
Phase Two · 14 Oct 2025
Awarded
Phase Two · 04 Dec 2025
Site Handover
Phase Three · 04 Dec 2025
Not Started
Phase Three · 04 Dec 2025
Ongoing
Phase Three · 04 Dec 2025
Completed
Phase Three · 19 Feb 2026