Kwa Kakulu Earthdam

Ongoing GoMC-PMTS-2026-9988
Project Description

Excavation of the reservoir, formation of embankment and spillway, protection works for embankment and spillway 

construction of pit latrine

Budget & Expenditure
Approved
KES 1.83M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2026-9988
  • WardKalawa
  • Sub-CountyMbooni
  • DepartmentDepartment of Finance, Planning, Budget and Revenu
  • DirectorateAdministration
  • FY2025/2026
  • SourceExchequer
  • Funded FromSelect funded from
  • CategoryNon Flagship
  • Start06 Jan 2026
  • End05 Jun 2026
Timeline
Cabinet Paper Approved
Phase One · 09 Oct 2025
Approved Requisition
Phase Two · 18 Nov 2025
Floated
Phase Two · 26 Nov 2025
Awarded
Phase Two · 22 Dec 2025
Site Handover
Phase Three · 22 Jan 2026
Not Started
Phase Three · 22 Jan 2026
Ongoing
Phase Three · 22 Jan 2026