Road Improvement Program – Fuel For Inhouse Works

Completed GoMC-PMTS-2024-3135
Project Description

Grading of Munathi - Kyuasi

Kitise – Ngunguuni – Kiangini river

Kiangini  River – Maau Eli 

Mbata – Mayuu – Manza – Ngunguuni – Ukokolani – Athiani

Budget & Expenditure
Approved
KES 900.0K
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-3135
  • WardKitise/Kithuki
  • Sub-CountyMakueni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 04 Oct 2023
Approved Requisition
Phase Two · 08 Dec 2023
Ongoing
Phase Three · 21 Mar 2024
Completed
Phase Three · 25 Sep 2024