Cultural Sites And Infrastructure Improvement- Mangelete sacret site and cultural center - fencing

Ongoing GoMC-PMTS-2025-6551
Project Description
Mangelete shrine and cultural  center fencing


Budget & Expenditure
Approved
KES 1.00M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-6551
  • WardHeadquaters
  • Sub-CountyHeadquarters
  • DepartmentDepartment of Trade, Marketing, Industry, Culture
  • DirectorateCulture
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start09 Jan 2026
  • End09 Apr 2026
Timeline
Cabinet Paper Approved
Phase One · 28 Oct 2025
Approved Requisition
Phase Two · 19 Nov 2025
Floated
Phase Two · 03 Dec 2025
Awarded
Phase Two · 09 Jan 2026
Site Handover
Phase Three · 09 Jan 2026
Not Started
Phase Three · 09 Jan 2026
Ongoing
Phase Three · 13 Jan 2026