Fencing Of Makindu Fire Station

Ongoing GoMC-PMTS-2025-4211
Budget & Expenditure
Approved
KES 900.0K
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-4211
  • WardMakindu
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Devolution, Public Service, Public
  • DirectorateSpecial Programs, Disaster Management and Emergency Services
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start14 Apr 2026
  • End14 May 2026
Timeline
Cabinet Paper Approved
Phase One · 28 Jan 2026
Approved Requisition
Phase Two · 26 Jan 2026
Floated
Phase Two · 23 Feb 0006
Awarded
Phase Two · 15 Apr 2026
Site Handover
Phase Three · 14 Apr 2026
Not Started
Phase Three · 14 Apr 2026
Ongoing
Phase Three · 15 Apr 2026