Uvileni Market Toilet

Completed GoMC-PMTS-2024-8181
Project Description

Construction of  3 door pit latrine  and urinal at Uvileni market

Budget & Expenditure
Approved
KES 1.00M
Contract
KES 599.4K
Spent
KES 599.4K
Utilisation
59.9%
Budget Utilisation
Gallery (3 photos)
Uvileni Public Toilet
Uvileni Public Toilet
Uvileni Public Toilet
Uvileni Public Toilet
Uvileni Public Toilet
Uvileni Public Toilet
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8181
  • WardNguumo
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Trade, Marketing, Industry, Culture
  • DirectorateTrade
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start11 Mar 2024
  • End11 Jun 2024
Timeline
Cabinet Paper Approved
Phase One · 27 Aug 2023
Approved Requisition
Phase Two · 09 Nov 2023
Floated
Phase Two · 17 Jan 2024
Awarded
Phase Two · 04 Mar 2024
Site Handover
Phase Three · 11 Mar 2024
Not Started
Phase Two · 11 Mar 2024
Ongoing
Phase Three · 11 Mar 2024
Completed
Phase Three · 20 Jun 2024
Completed
Phase Three · 20 Jun 2024