Kwa Mulinge Drift

Completed GoMC-PMTS-2024-3298
Project Description

Kwa Mulinge drift- construction of a drift, culverts, installation of gabions and excavation of roads for water structures

Budget & Expenditure
Approved
KES 1.47M
Contract
KES 1.40M
Spent
KES 1.40M
Utilisation
95.2%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-3298
  • WardKikumini/Muvau
  • Sub-CountyMakueni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start18 Apr 2024
  • End18 Jun 2024
Timeline
Cabinet Paper Approved
Phase One · 20 Sep 2023
Approved Requisition
Phase Two · 07 Dec 2023
Floated
Phase Two · 04 Mar 2024
Awarded
Phase Two · 04 Apr 2024
Site Handover
Phase Three · 17 Apr 2024
Not Started
Phase Two · 17 Apr 2024
Ongoing
Phase Three · 18 Apr 2024
Completed
Phase Three · 03 Dec 2024