Matiliku Subcounty Hospital (dental Chair, Accessories And Other Smal Equipment)

Completed Flagship GoMC-PMTS-2024-4467
Project Description

Renovation works and supply of dental chair

Budget & Expenditure
Approved
KES 46.0K
Contract
KES 1.25M
Spent
KES 1.24M
Utilisation
100%
Budget Utilisation
Gallery (1 photos)
Matiliku Dental Chair
Matiliku Dental Chair
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-4467
  • WardNzaui/Kilili/Kalamba
  • Sub-CountyMakueni
  • DepartmentDepartment of Health Services
  • DirectorateCurative and Rehabilitative Services
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryFlagship
  • Start20 Mar 2024
  • End18 May 2024
Timeline
Cabinet Paper Approved
Phase One · 22 Nov 2023
Approved Requisition
Phase Two · 26 Nov 2023
Floated
Phase Two · 09 Feb 2024
Awarded
Phase Two · 18 Mar 2024
Site Handover
Phase Three · 02 Feb 2024
Not Started
Phase Two · 02 Feb 2024
Ongoing
Phase Three · 05 Feb 2024
Completed
Phase Three · 27 Mar 2024