Construction Of Ward Hod Offices (kilungu Ward Head Quarters Offices) -construction Of Ward Headquarter Offices To Host All The Ward Head Of Departments (hod). The Offices To Have Common Store And Kitchen. The Offices To Have An Ict Centre With Wifi And A Mini Hall Of 50 Seater.

Ongoing GoMC-PMTS-2025-8873
Project Description

Construction of Ward HoD Offices  (Kilungu Ward Head Quarters Offices) -Construction of Ward headquarter Offices to host all the ward Head of Departments (HoD).The offices to have common store and Kitchen. The offices to have an ICT center with WIFI and a mini hall of 50 seater.

Budget & Expenditure
Approved
KES 4.00M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-8873
  • WardHeadquaters
  • Sub-CountyHeadquarters
  • DepartmentDepartment of Devolution, Public Service, Public
  • DirectorateCounty Administration
  • FY2025/2026
  • SourceExchequer
  • Funded FromHeadquaters
  • CategoryNon Flagship
  • Start13 Feb 2026
  • End30 Jun 2026
Timeline
Cabinet Paper Approved
Phase One · 20 Jan 2026
Approved Requisition
Phase Two · 22 Jan 2026
Floated
Phase Two · 09 Feb 2026
Awarded
Phase Two · 13 Feb 2026
Site Handover
Phase Three · 16 Feb 2026
Not Started
Phase Three · 16 Feb 2026
Ongoing
Phase Three · 18 Feb 2026