Green Energy Promotion

Completed Flagship GoMC-PMTS-2024-7350
Project Description

Installation of Solar photovoltaic  system at Makueni County Referral Hospital.

Installation of access ladders, walkways and fall protection systems 

Installation of 205k Wp solar system 

Installation of two 100ktl inverters

Installation of AC combiner box

Installation of solar system to the frid and generator 

Installation of project monitoring and evaluation system 

Budget & Expenditure
Approved
KES 28.42M
Contract
KES 26.39M
Spent
KES 28.42M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-7350
  • WardHeadquaters
  • Sub-CountyHeadquarters
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateEnergy
  • FY2023/2024
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryFlagship
  • Start09 Apr 2024
  • End28 Jun 2024
Timeline
Cabinet Paper Approved
Phase One · 14 Dec 2023
Approved Requisition
Phase Two · 14 Dec 2023
Floated
Phase Two · 20 Dec 2023
Awarded
Phase Two · 22 Dec 2023
Site Handover
Phase Three · 26 Mar 2024
Not Started
Phase Two · 26 Mar 2024
Ongoing
Phase Three · 09 Apr 2024
Completed
Phase Three · 14 Jun 2024