Opening Of Matheani Kwa Nyaa Road

Completed GoMC-PMTS-2024-3113
Project Description

Road opening and grading of Matheani- kwa Nyaa road

Budget & Expenditure
Approved
KES 2.50M
Contract
KES 2.37M
Spent
KES 2.37M
Utilisation
94.9%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-3113
  • WardKitise/Kithuki
  • Sub-CountyMakueni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start18 Apr 2024
  • End18 Jun 2024
Timeline
Cabinet Paper Approved
Phase One · 06 Feb 2024
Approved Requisition
Phase Two · 08 Feb 2024
Floated
Phase Two · 20 Feb 2024
Awarded
Phase Two · 04 Apr 2024
Site Handover
Phase Three · 15 Apr 2024
Not Started
Phase Two · 15 Apr 2024
Ongoing
Phase Three · 18 Apr 2024
Completed
Phase Three · 28 Jun 2024