Road Structures And Protection Works

Completed GoMC-PMTS-2024-8693
Project Description

Excavation and filling for structure

installation of culverts and drainage works

Backfilling

Budget & Expenditure
Approved
KES 2.94M
Contract
KES 2.37M
Spent
KES 2.85M
Utilisation
96.9%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8693
  • WardMavindini
  • Sub-CountyMakueni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start18 Apr 2024
  • End18 Jun 2024
Timeline
Cabinet Paper Approved
Phase One · 06 Feb 2024
Approved Requisition
Phase Two · 08 Feb 2024
Floated
Phase Two · 20 Feb 2024
Awarded
Phase Two · 04 Apr 2024
Site Handover
Phase Three · 10 Apr 2024
Not Started
Phase Two · 12 Apr 2024
Ongoing
Phase Three · 12 Apr 2024
Completed
Phase Three · 21 May 2024