Levelling Of Kiima Kiu Play Ground

Not Started GoMC-PMTS-2025-6029
Project Description

Levelling of Kiima Kiu Play ground

Budget & Expenditure
Approved
KES 1.00M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-6029
  • WardKiima Kiu/Kalanzoni
  • Sub-CountyKilome
  • DepartmentDepartment of Gender, Children, Youth, Sports and
  • DirectorateSports
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start11 Feb 2026
  • End11 Jul 2026
Timeline
Cabinet Paper Approved
Phase One · 20 Nov 2025
Approved Requisition
Phase Two · 15 Dec 2025
Floated
Phase Two · 15 Jan 2026
Floated
Phase Two · 15 Jan 2026
Awarded
Phase Two · 11 Feb 2026
Site Handover
Phase Three · 24 Feb 2026
Not Started
Phase Three · 24 Feb 2026