Fuel/machine Hire For Grading Of Sekeleni-ilatu-kalembe Raha Road

Completed GoMC-PMTS-2024-8628
Project Description

Bush clearing done,

Road opening and grading (9km) 

- Construction of mitre drains

Budget & Expenditure
Approved
KES 1.96M
Contract
KES 1.80M
Spent
KES 1.80M
Utilisation
91.8%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8628
  • WardNguumo
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start22 Feb 2024
  • End23 Feb 2024
Timeline
Cabinet Paper Approved
Phase One · 20 Sep 2023
Approved Requisition
Phase Two · 07 Dec 2023
Floated
Phase Two · 21 Dec 2023
Awarded
Phase Two · 22 Feb 2024
Site Handover
Phase Three · 22 Feb 2024
Not Started
Phase Two · 22 Feb 2024
Ongoing
Phase Three · 26 Feb 2024
Completed
Phase Three · 20 Mar 2024