Muliluni-kiambani Water Project

Completed Flagship GoMC-PMTS-2025-2263
Project Description


Budget & Expenditure
Approved
KES 10.00M
Contract
KES 10.81M
Spent
KES 10.81M
Utilisation
100%
Budget Utilisation
Gallery (3 photos)
Muliluni Kiambani Water Project - Kiambani Water Kiosk
Muliluni Kiambani Water Project - Kiambani Water Kiosk
Muliluni Kiambani Water Project - Communal Water Point
Muliluni Kiambani Water Project - Communal Water Point
Muliluni Kiambani Water Project
Muliluni Kiambani Water Project
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-2263
  • WardMasongaleni
  • Sub-CountyKibwezi East
  • DepartmentDepartment of Lands, Urban Planning and Developmen
  • DirectorateEnvironment and Climate Change
  • FY2024/2025
  • SourceConditional grants
  • Funded FromHeadquaters
  • CategoryFlagship
  • Start15 Oct 2024
  • End17 Mar 2025
Timeline
Cabinet Paper Approved
Phase One · 28 Aug 2024
Approved Requisition
Phase Two · 04 Nov 2024
Floated
Phase Two · 16 Sep 2024
Awarded
Phase Two · 06 Oct 2024
Site Handover
Phase Three · 15 Oct 2024
Not Started
Phase Three · 15 Oct 2024
Ongoing
Phase Three · 30 Oct 2024
Completed
Phase Three · 07 Feb 0005