Wautu Kyangaati Sand Dam And Water Project

Completed Flagship GoMC-PMTS-2025-4004
Project Description

Sand dam construction,Reinforced concrete sump, Solar pumping system,Raising main, 100m3 masonry water tank and communal water access point at Kwa Chief,Construction of Kyangaati-wautu gravity line with 2 communal water points,Agroforestry and Riparian land conservation initiative(5000 Avocado and 400 Assorted riparian tree species), Community outreach program on SLM and Best practices in Agroforestry.

Budget & Expenditure
Approved
KES 15.50M
Contract
KES 0.00
Spent
KES 13.62M
Utilisation
87.9%
Budget Utilisation
Gallery (3 photos)
Wautu Kyangaati Sand Dam
Wautu Kyangaati Sand Dam
Wautu Kyangaati Concrete Sump
Wautu Kyangaati Concrete Sump
Wautu Kyangaati Water Project - Masonry Tank
Wautu Kyangaati Water Project - Masonry Tank
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-4004
  • WardIlima
  • Sub-CountyKaiti
  • DepartmentDepartment of Lands, Urban Planning and Developmen
  • DirectorateLands, Urban Planning and Development
  • FY2024/2025
  • SourceConditional grants
  • Funded FromHeadquaters
  • CategoryFlagship
  • Start25 Oct 2024
  • End25 Mar 2025
Timeline
Cabinet Paper Approved
Phase One · 16 May 2024
Approved Requisition
Phase Two · 22 May 2024
Floated
Phase Two · 16 Aug 2024
Awarded
Phase Two · 06 Oct 2024
Site Handover
Phase Three · 25 Oct 0024
Not Started
Phase Three · 25 Oct 0024
Ongoing
Phase Three · 16 Dec 2024
Completed
Phase Three · 16 Apr 2025