Development of Municipal Integrated Development Plan (IDEP) and Municipal Spatial Plan

Completed GoMC-PMTS-2024-5338
Project Description
  • Development Plan (IDEP) and Municipal Spatial Plan
Budget & Expenditure
Approved
KES 10.00M
Contract
KES 9.88M
Spent
KES 9.88M
Utilisation
98.8%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-5338
  • WardEmali/Mulala
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Lands, Urban Planning and Developmen
  • DirectorateEmali/Sultan Hamud Municipality
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start15 Nov 2023
  • End15 Jan 2024
Timeline
Cabinet Paper Approved
Phase One · 01 Aug 2023
Approved Requisition
Phase Two · 02 Aug 2023
Floated
Phase Two · 28 Aug 2023
Awarded
Phase Two · 28 Aug 2023
Site Handover
Phase Three · 15 Sep 2023
Not Started
Phase Two · 15 Sep 2023
Ongoing
Phase Three · 15 Nov 2023
Completed
Phase Three · 15 Jan 2024