Installation Of Floodlight At Utithi And Yumbuni

Ongoing GoMC-PMTS-2025-3325
Project Description
Installation of 10.5M solar lights (2*150W)at  Utithi and Yumbuni


Budget & Expenditure
Approved
KES 600.0K
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-3325
  • WardThange
  • Sub-CountyKibwezi East
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateEnergy
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start06 Jan 2026
  • End06 Apr 2026
Timeline
Cabinet Paper Approved
Phase One · 04 Sep 2025
Approved Requisition
Phase Two · 22 Sep 2025
Floated
Phase Two · 03 Oct 2025
Awarded
Phase Two · 22 Dec 2025
Site Handover
Phase Three · 05 Jan 2026
Not Started
Phase Three · 05 Jan 2026
Ongoing
Phase Three · 06 Jan 2026