Kikumini Model Health Center

Completed Flagship GoMC-PMTS-2024-8702
Project Description

Construction of new Outpatient block

Budget & Expenditure
Approved
KES 4.59M
Contract
KES 4.98M
Spent
KES 1.30M
Utilisation
28.4%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8702
  • WardKikumini/Muvau
  • Sub-CountyMakueni
  • DepartmentDepartment of Health Services
  • DirectorateCurative and Rehabilitative Services
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryFlagship
  • Start30 Mar 2024
  • End25 May 2024
Timeline
Cabinet Paper Approved
Phase One · 02 Nov 2023
Approved Requisition
Phase Two · 08 Feb 2024
Floated
Phase Two · 28 Feb 2024
Awarded
Phase Two · 29 Mar 2024
Site Handover
Phase Three · 20 Mar 2024
Not Started
Phase Two · 20 Mar 2024
Ongoing
Phase Three · 25 Mar 2024
Completed
Phase Three · 06 Dec 2024