Opening and grading along Makutano - Mbeleti -Kaseve Road, Kwa Ann Musomba - Kwa Nzola road, Kwa Linda-Kawia Nguni road

Completed GoMC-PMTS-2025-4412
Project Description
 Opening and grading along Makutano - Mbeleti -Kaseve Road,  Kwa Ann Musomba - Kwa Nzola road, Kwa Linda-Kawia Nguni road


Budget & Expenditure
Approved
KES 3.00M
Contract
KES 2.85M
Spent
KES 2.85M
Utilisation
94.8%
Budget Utilisation
Citizen Feedback
west cluster 16 Aug 2026
Opening and grading of Iviani - West Ngosini catholic church - Kwa Kitavi boundary-Mutevu- through Manyanzani earth dam – to Kwa Maithya road. Opening and grading of Kwa Ann Musomba-Mangauni-Kwa Li

this is not true reflection on the ground. It appears that this is for PR purposes. reflect whats actual. our community have lost faith on misinformation. Do an actual audit to see if this so called, opening and grading of Iviani - West Ngosini catholic church - Kwa Kitavi boundary-Mutevu- through Manyanzani earth dam to Kwa Maithya road. Opening and grading of Kwa Ann Musomba-Mangauni-Kwa Linda-Kawia Nguni road, was done and compoleted as alledged herewith. we are yet to see a miningful partiticipation. we believe their is a PMC to report on the same.

Official Response:

The County Government appreciates the concern raised.. The works undertaken included opening and grading of Makutano–Mbeleti–Kaseve Road, Kwa Ann Musomba–Kwa Nzola Road, and Kwa Linda–Kawia Nguni Road. Following data collection by the County Engineers, the initial project scope was revised accordingly and the identified works were subsequently implemented. The County Government remains committed to ensuring accurate reporting, transparency and accountability in the implementation of development projects. Thank you

member 16 Aug 2026
Opening and grading of Iviani - West Ngosini catholic church - Kwa Kitavi boundary-Mutevu- through Manyanzani earth dam to Kwa Maithya road. Opening and grading of Kwa Ann Musomba-Mangauni-Kwa Linda-

we are informed by the adm. that money got finished. how did this happen? we demand an audit and transparency towards our funds. this Ward is known to have huge allocations to roads, yet on the ground its nothing but a disgrace...ROADS alone hv 12.5m ksh in one financial year. agriculture zero. Our farmers continue to beg for seedling, vaccintion, training, etc

Official Response:

The County Government appreciates the concern raised.. The works undertaken included opening and grading of Makutano–Mbeleti–Kaseve Road, Kwa Ann Musomba–Kwa Nzola Road, and Kwa Linda–Kawia Nguni Road. Following data collection by the County Engineers, the initial project scope was revised accordingly and the identified works were subsequently implemented. The County Government remains committed to ensuring accurate reporting, transparency and accountability in the implementation of development projects. Thank you

west cluster 16 Aug 2026
Opening and grading of Iviani - West Ngosini catholic church - Kwa Kitavi boundary-Mutevu- through Manyanzani earth dam – to Kwa Maithya road. Opening and grading of Kwa Ann Musomba-Mangauni-Kwa Li

this is not true reflection on the ground. It appears that this is for PR purposes. reflect whats actual. our community have lost faith on misinformation. Do an actual audit to see if this so called, opening and grading of Iviani - West Ngosini catholic church - Kwa Kitavi boundary-Mutevu- through Manyanzani earth dam to Kwa Maithya road. Opening and grading of Kwa Ann Musomba-Mangauni-Kwa Linda-Kawia Nguni road, was done and compoleted as alledged herewith. we are yet to see a miningful partiticipation. we believe their is a PMC to report on the same.

Official Response:

The County Government appreciates the concern raised.. The works undertaken included opening and grading of Makutano–Mbeleti–Kaseve Road, Kwa Ann Musomba–Kwa Nzola Road, and Kwa Linda–Kawia Nguni Road. Following data collection by the County Engineers, the initial project scope was revised accordingly and the identified works were subsequently implemented. The County Government remains committed to ensuring accurate reporting, transparency and accountability in the implementation of development projects. Thank you

Project Details
  • RefGoMC-PMTS-2025-4412
  • WardKikumini/Muvau
  • Sub-CountyMakueni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start11 Nov 2025
  • End12 May 2026
Timeline
Cabinet Paper Approved
Phase One · 27 Oct 2025
Approved Requisition
Phase Two · 29 Sep 2025
Floated
Phase Two · 02 Oct 2025
Floated
Phase Two · 02 Oct 2025
Awarded
Phase Two · 04 Nov 2025
Site Handover
Phase Three · 12 Nov 2025
Not Started
Phase Three · 12 Nov 2025
Ongoing
Phase Three · 13 Nov 2025
Completed
Phase Three · 22 Jun 2026