Kwa Kitei Drift

Completed GoMC-PMTS-2024-7064
Project Description
Kwa Kitei Drift -Construction of 35m drift and protection works
Budget & Expenditure
Approved
KES 3.43M
Contract
KES 3.32M
Spent
KES 3.32M
Utilisation
96.8%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-7064
  • WardMbitini
  • Sub-CountyMakueni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start22 Apr 2024
  • End22 Jun 2024
Timeline
Cabinet Paper Approved
Phase One · 06 Feb 2024
Approved Requisition
Phase Two · 08 Feb 2024
Floated
Phase Two · 20 Feb 2024
Awarded
Phase Two · 18 Apr 2024
Site Handover
Phase Three · 18 Apr 2024
Not Started
Phase Two · 18 Apr 2024
Ongoing
Phase Three · 22 Apr 2024
Completed