Kikima Town/markets Development Program -phased Programme.- Cabro Paving Kikima Victoria Hotel- Knut Offices, Machakos And Tawa Busparks, Walkway Construction From Kcb To Amazon Petrol Station And Markets Street Lighting

Ongoing GoMC-PMTS-2025-4904
Project Description

1. Installation of 20M (6*400W) high floodlight at Kali and Nzeveni markets 

2. Installation of streetlights at Kwa Mbisu market (15M concrete pole, 4No.lantern c/w all accessories, bolts and nuts, 400W LED fittings)

3. Installation of the streetlights at Ithamaa Junction (10M concrete pole, 1No.lantern  c/w all accessories, bolts and nuts, 120W LED fittings)

4. 5km parking/access road Cabro paving Kikima victoria hotel- KNUT offices section

Budget & Expenditure
Approved
KES 10.00M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Components (1)
Component Budget Expenditure Status
Cabro paving of Kikima victoria hotel- KNUT offices, machakos and Tawa busparks, walkway construction from KCB to Amazon petrol station and Markets street lighting KES 5.00M KES 4.05M Completed
Gallery (1 photos)
Kikima Streetlights
Kikima Streetlights
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-4904
  • WardMbooni
  • Sub-CountyMbooni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start06 Nov 2025
  • End30 Apr 2026
Timeline
Cabinet Paper Approved
Phase One · 21 Aug 2025
Approved Requisition
Phase Two · 22 Sep 2025
Floated
Phase Two · 01 Oct 2025
Awarded
Phase Two · 30 Oct 2025
Site Handover
Phase Three · 06 Nov 2025
Not Started
Phase Three · 06 Nov 2025
Ongoing
Phase Three · 10 Nov 2025