Kithumani- Mbalani-Katundu Drift

Completed GoMC-PMTS-2024-1711
Project Description

culverts installation and spot gravelling of Kithumani- Mbalani- Katundu Drift

Budget & Expenditure
Approved
KES 3.92M
Contract
KES 3.92M
Spent
KES 3.79M
Utilisation
96.8%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-1711
  • WardMbitini
  • Sub-CountyMakueni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start07 Mar 2024
  • End07 Jun 2024
Timeline
Cabinet Paper Approved
Phase One · 20 Sep 2023
Approved Requisition
Phase Two · 18 Jan 2024
Floated
Phase Two · 07 Feb 2024
Awarded
Phase Two · 07 Mar 2024
Site Handover
Phase Three · 07 Mar 2024
Not Started
Phase Two · 07 Mar 2024
Ongoing
Phase Three · 07 Mar 2024
Completed
Phase Three · 26 Jun 2023