Construction Of Boda Boda Shed Atkwa Ndunda And Ngoni Market

Ongoing GoMC-PMTS-2025-7756
Project Description

Construction of a shed

Budget & Expenditure
Approved
KES 1.00M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-7756
  • WardKisau/Kiteta
  • Sub-CountyMbooni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start17 Mar 2026
  • End30 Jul 2026
Timeline
Cabinet Paper Approved
Phase One · 27 Oct 2025
Approved Requisition
Phase Two · 10 Nov 2025
Floated
Phase Two · 28 Jan 2026
Awarded
Phase Two · 16 Mar 2026
Site Handover
Phase Three · 23 Mar 2026
Not Started
Phase Three · 23 Mar 2026
Ongoing
Phase Three · 27 Mar 2026