Construction Of Muaani Drift And Murraming Of Jones To Muaani Girls Road

Completed GoMC-PMTS-2024-8387
Project Description
Construction of Muaani drift, road grading, gravelling, Installation of culverts and gabions along Jones to Muaani Girls road
Budget & Expenditure
Approved
KES 4.90M
Contract
KES 4.76M
Spent
KES 4.66M
Utilisation
95.2%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8387
  • WardWote/Nziu
  • Sub-CountyMakueni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start21 Mar 2024
  • End20 May 2024
Timeline
Cabinet Paper Approved
Phase One · 20 Sep 2023
Approved Requisition
Phase Two · 18 Jan 2024
Floated
Phase Two · 07 Feb 2024
Awarded
Phase Two · 12 Mar 2024
Site Handover
Phase Three · 20 Mar 2024
Not Started
Phase Two · 20 Mar 2024
Ongoing
Phase Three · 21 Mar 2024
Completed
Phase Three · 28 Nov 2024