Ict Inftrastructure - Lan

Completed GoMC-PMTS-2024-1426
Project Description
  • Installation of LAN in Emali/Sultan Municipality offices at Emali
Budget & Expenditure
Approved
KES 2.00M
Contract
KES 2.00M
Spent
KES 2.00M
Utilisation
99.9%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-1426
  • WardEmali/Mulala
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Lands, Urban Planning and Developmen
  • DirectorateEmali/Sultan Hamud Municipality
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start21 Nov 2023
  • End05 Feb 2024
Timeline
Cabinet Paper Approved
Phase One · 11 Aug 2023
Approved Requisition
Phase Two · 28 Aug 2023
Floated
Phase Two · 13 Dec 2023
Awarded
Phase Two · 15 Nov 2023
Site Handover
Phase Three · 16 Nov 2023
Not Started
Phase Two · 16 Nov 2023
Ongoing
Phase Three · 22 Nov 2023
Completed
Phase Three · 05 Feb 2024