Electrification Of Kyanginywa Dispensary

Ongoing GoMC-PMTS-2025-4830
Project Description

Electrical fittings works at the dispensary 

Budget & Expenditure
Approved
KES 500.0K
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-4830
  • WardKikumbulyu South
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Health Services
  • DirectorateCurative and Rehabilitative Services
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start22 Oct 2025
  • End03 Nov 2025
Timeline
Cabinet Paper Approved
Phase One · 01 Oct 2025
Approved Requisition
Phase Two · 06 Oct 2025
Floated
Phase Two · 11 Oct 2025
Awarded
Phase Two · 16 Oct 2025
Site Handover
Phase Three · 06 Nov 2025
Not Started
Phase Three · 06 Nov 2025
Ongoing
Phase Three · 12 Nov 2025