Renovation Of Nzeveni Health Centre Maternity

Ongoing GoMC-PMTS-2025-9773
Project Description

Partitioning of rooms, painting , ceiling and toilet  construction 

Budget & Expenditure
Approved
KES 1.50M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2025-9773
  • WardIvingoni/Nzambani
  • Sub-CountyKibwezi East
  • DepartmentDepartment of Health Services
  • DirectorateCurative and Rehabilitative Services
  • FY2025/2026
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start27 Oct 2025
  • End03 Jun 2026
Timeline
Cabinet Paper Approved
Phase One · 04 Oct 2025
Approved Requisition
Phase Two · 09 Oct 2025
Floated
Phase Two · 13 Oct 2025
Awarded
Phase Two · 18 Oct 2025
Site Handover
Phase Three · 04 Nov 2025
Not Started
Phase Three · 04 Nov 2025
Ongoing